33 U.S.C. § 515 — Contracts for project; guaranty of cost

U.S.C. Title 33 - NAVIGATION AND NAVIGABLE WATERS 33 U.S.C. United States Code, 2023 Edition Title 33 - NAVIGATION AND NAVIGABLE WATERS CHAPTER 11 - BRIDGES OVER NAVIGABLE WATERS SUBCHAPTER II - ALTERATION OF BRIDGES Sec. 515 - Contracts for project; guaranty of cost From the U.S. Government Publishing Office, www.gpo.gov

§515. Contracts for project; guaranty of cost

After approval of such general plans and specifications by the Secretary, and after notification of such approval, the bridge owner shall, in such manner and within such times as the Secretary may prescribe, take bids for the alteration of such bridge in accordance with such general plans and specifications. All bids, including any bid for all or part of the project submitted by the bridge owner, shall be submitted to the Secretary, together with a recommendation by the bridge owner as to the most competent bid or bids, and at the same time the bridge owner shall submit to the Secretary a written guaranty that the total cost of the project, including the cost of such work as is to be performed by the bridge owner and not included in the work to be performed by contract, shall not exceed the sum stated in said guaranty. The Secretary may direct the bridge owner to reject all bids and to take new bids, or may authorize the bridge owner to proceed with the project, by contract, or partly by contract and partly by the bridge owner, or wholly by the bridge owner. Upon such authorization and fixing of the proportionate shares of the cost as provided in section 516 of this title, the bridge owner shall, within a reasonable time to be prescribed by the Secretary, proceed with the work of alteration; and the cost thereof shall be borne by the United States and by the bridge owner, as provided in sections 516 and 517 of this title: Provided, That where funds have been appropriated for part only of a project, the bridge owner may take bids for part only of the work. In the event the bridge owner proceeds with the alteration through the taking of successive partial bids, the bridge owner shall, if required by the Secretary, submit a revised guaranty of cost after bids are accepted for successive parts of the work.

(June 21, 1940, ch. 409, §5, 54 Stat. 498; Pub. L. 85–640, §1(a), (b), Aug. 14, 1958, 72 Stat. 595.)

Editorial Notes

Amendments 1958—Pub. L. 85–640 struck out provisions which required bridge owner to take bids within 90 days after notification of approval of general plans and specifications, and inserted provisions permitting the taking of partial bids where funds have been appropriated for part of a project, and requiring the bridge owner, if requested, to submit a revised guaranty of cost.

Source: uscode.house.gov — public domain Official Source ↗
Root-LD Entity Data
◈ Machine-Readable Provenance Record Root-LD v1.0 · boisestandard.org
Federation ID
BS-USC33-SEC-7A55BD
Entity Class
STATUTE / FEDERAL-CODE-SECTION
Domain Signature
boisestandard.org
Citation
33 U.S.C. § 515
Jurisdiction
Federal — United States
Status
✓ ACTIVE
Source
PRIMARY-SOURCE
Source Verified
✓ TRUE
Content Hash
16fdd2dd952bdab8...
Semantic Edges
Pending — corpus passes queued
The statutory text of 33 U.S.C. § 515 is reproduced from the official United States Code as published by the Office of the Law Revision Counsel of the U.S. House of Representatives (uscode.house.gov).
Navigate Corpus — Title 33
◈ Provenance
boisestandard.org United States Law U.S. Code Title 33 33 U.S.C. § 515