§ 750.307 FHWA project approval. Authorization to proceed with acquisitions on a sign removal project shall not be issued until such time as the State has submitted to FHWA the following: (a) A general description of the project. (b) The total number of signs to be acquired. (c) The total estimated cost of the sign removal project, including a breakdown of incidental, acquisition and removal costs.
Source: ecfr.gov · govinfo.gov — public domain
Official Source ↗
Root-LD Entity Data
◈ Machine-Readable Provenance Record
Root-LD v1.0 · boisestandard.org
Federation ID
BS-CFR23-SEC-785C64
Entity Class
REGULATION / FEDERAL-CFR-SECTION
Domain Signature
boisestandard.org
Citation
23 C.F.R. § 750.307
Corpus
CFR — Code of Federal Regulations
Status
✓ ACTIVE
Source
PRIMARY-SOURCE
Source Verified
✓ TRUE
Content Hash
2dfd7edc5fdbef65...
Semantic Edges
Pending — corpus passes queued
The regulatory text of 23 C.F.R. § 750.307 is reproduced from the official Code of Federal Regulations as published by the Office of the Federal Register and the National Archives and Records Administration.
Navigate Corpus — Title 23 C.F.R.
Title 23 — Highways
23 C.F.R. § 1.123 C.F.R. § 1.223 C.F.R. § 1.323 C.F.R. § 1.523 C.F.R. § 1.723 C.F.R. § 1.823 C.F.R. § 1.923 C.F.R. § 1.1123 C.F.R. § 1.2323 C.F.R. § 1.2723 C.F.R. § 1.2823 C.F.R. § 1.3223 C.F.R. § 1.3323 C.F.R. § 1.3523 C.F.R. § 1.3623 C.F.R. § 140.50123 C.F.R. § 140.50323 C.F.R. § 140.50523 C.F.R. § 140.60123 C.F.R. § 140.60223 C.F.R. § 140.60323 C.F.R. § 140.60423 C.F.R. § 140.60523 C.F.R. § 140.60623 C.F.R. § 140.60723 C.F.R. § 140.60823 C.F.R. § 140.60923 C.F.R. § 140.61023 C.F.R. § 140.61123 C.F.R. § 140.612
23 C.F.R. — public domain
← All Legislation