23 C.F.R. · Highways
23 C.F.R. § 636.513

Are limited negotiations allowed prior to contract execution?

Title 23 C.F.R. ● ACTIVE Primary Source
Regulatory Text

23 C.F.R. § 636.513 — Are limited negotiations allowed prior to contract execution?

§ 636.513 Are limited negotiations allowed prior to contract execution? (a) Yes, after the source selection but prior to contract execution, you may conduct limited negotiations with the selected design-builder to clarify any remaining issues regarding scope, schedule, financing or any other information provided by that offeror. You must comply with the provisions of § 636.507 in the exchange of this information. (b) Limited negotiations conducted under this section may include negotiations necessary to incorporate the ideas and concepts from unsuccessful offerors into the contract if a stipend is offered by the contracting agency and accepted by the unsuccessful offeror and if the requirements of section 636.113 are met. [67 FR 75926, Dec. 10, 2002, as amended at 73 FR 77502, Dec. 19, 2008]

Source: ecfr.gov · govinfo.gov — public domain Official Source ↗
Root-LD Entity Data
◈ Machine-Readable Provenance Record Root-LD v1.0 · boisestandard.org
Federation ID
BS-CFR23-SEC-C74E71
Entity Class
REGULATION / FEDERAL-CFR-SECTION
Domain Signature
boisestandard.org
Citation
23 C.F.R. § 636.513
Corpus
CFR — Code of Federal Regulations
Status
✓ ACTIVE
Source
PRIMARY-SOURCE
Source Verified
✓ TRUE
Content Hash
2f44bf26603a2e2c...
Semantic Edges
Pending — corpus passes queued
The regulatory text of 23 C.F.R. § 636.513 is reproduced from the official Code of Federal Regulations as published by the Office of the Federal Register and the National Archives and Records Administration.
Navigate Corpus — Title 23 C.F.R.
◈ Provenance
boisestandard.org United States Law CFR Title 23 23 C.F.R. § 636.513