23 C.F.R. § 636.201 — What selection procedures and award criteria may be used?

§ 636.201 What selection procedures and award criteria may be used? You should consider using two-phase selection procedures for all design-build projects. However, if you do not believe two-phase selection procedures are appropriate for your project (based on the criteria in § 636.202), you may use a single phase selection procedure or the modified-design-build contracting method. The following procedures are available: Selection procedure Criteria for using a selection procedure Award criteria options (a) Two-Phase Selection Procedures (RFQ followed by RFP) § 636.202 Lowest price, Adjusted low-bid (price per quality point), meets criteria/low bid, weighted criteria process, fixed price/best design, best value. (b) Single Phase (RFP) Project not meeting the criteria in § 636.202 All of the award criteria in item (a) of this table. (c) Modified Design-Build (may be one or two phases) Any project Lowest price technically acceptable.

Source: ecfr.gov · govinfo.gov — public domain Official Source ↗
Root-LD Entity Data
◈ Machine-Readable Provenance Record Root-LD v1.0 · boisestandard.org
Federation ID
BS-CFR23-SEC-B5D99D
Entity Class
REGULATION / FEDERAL-CFR-SECTION
Domain Signature
boisestandard.org
Citation
23 C.F.R. § 636.201
Corpus
CFR — Code of Federal Regulations
Status
✓ ACTIVE
Source
PRIMARY-SOURCE
Source Verified
✓ TRUE
Content Hash
09427d570ad076fa...
Semantic Edges
Pending — corpus passes queued
The regulatory text of 23 C.F.R. § 636.201 is reproduced from the official Code of Federal Regulations as published by the Office of the Federal Register and the National Archives and Records Administration.
Navigate Corpus — Title 23 C.F.R.
◈ Provenance
boisestandard.org United States Law CFR Title 23 23 C.F.R. § 636.201