18 C.F.R. § 12.41 — Corrective measures.

§ 12.41 Corrective measures. (a) Corrective measures. For items identified during a periodic inspection or comprehensive assessment as requiring corrective action, the following conditions apply: (1) Corrective plan and schedule. (i) Not later than 60 days after a report on a periodic inspection or comprehensive assessment is filed with the Regional Engineer, the licensee must submit to the Regional Engineer a plan and schedule for addressing the recommendations of the independent consultant(s) and for investigating, designing, and carrying out any corrective measures that the licensee proposes to implement. (ii) The plan and schedule may include any proposal, including taking no action, that the licensee considers a preferable alternative to any corrective measure recommended in the report of the independent consultant(s). Any proposed alternative must be accompanied by the licensee's complete justification and detailed analysis and evaluation in support of that alternative. (2) Carrying out the plan. The licensee must complete all corrective measures in accordance with the plan and schedule submitted to, and approved or modified by, the Regional Engineer, and on an annual basis must submit a status report on the corrective measures until all have been completed. (3) Extension of time. For good cause shown, the Regional Engineer may extend the time for filing the plan and schedule required by this section. (b) Emergency corrective measures. The licensee must provide that if, in the course of a periodic inspection or comprehensive assessment conducted under this subpart D, an independent consultant discovers any condition for which emergency corrective measures are advisable, such as a condition affecting the safety of a project or project works as defined in § 12.3(b)(4) of this part, the independent consultant must immediately notify the licensee and the licensee must report that condition to the Regional Engineer pursuant to § 12.10(a) of this part. Emergency corrective measures must be included in the corrective plan and schedule required by paragraph (a)(1) of this section, and are also subject to paragraphs (a)(2) and (a)(3) of this section.

Source: ecfr.gov · govinfo.gov — public domain Official Source ↗
Root-LD Entity Data
◈ Machine-Readable Provenance Record Root-LD v1.0 · boisestandard.org
Federation ID
BS-CFR18-SEC-9B6043
Entity Class
REGULATION / FEDERAL-CFR-SECTION
Domain Signature
boisestandard.org
Citation
18 C.F.R. § 12.41
Corpus
CFR — Code of Federal Regulations
Status
✓ ACTIVE
Source
PRIMARY-SOURCE
Source Verified
✓ TRUE
Content Hash
7b352e65886793ec...
Semantic Edges
Pending — corpus passes queued
The regulatory text of 18 C.F.R. § 12.41 is reproduced from the official Code of Federal Regulations as published by the Office of the Federal Register and the National Archives and Records Administration.
Navigate Corpus — Title 18 C.F.R.
◈ Provenance
boisestandard.org United States Law CFR Title 18 18 C.F.R. § 12.41