Idaho Code § 61-516 — Priority Designation For Electric Transmission Projects.

TITLE 61 PUBLIC UTILITY REGULATION CHAPTER 5 POWERS AND DUTIES OF PUBLIC UTILITIES COMMISSION 61-516. priority designation for electric transmission projects. (1) The legislature finds that the timely review and permitting of electric transmission facilities is critical to the well-being of the citizens and the economy of this state and the region. The legislature further finds that enactment of this section is necessary to promote the public interest. The purpose of this section is for the public utilities commission to determine whether the construction of electric transmission facilities should be designated to receive priority processing by state agencies. This section is not intended to affect a state agency’s decision-making authority to approve, deny or condition an application to construct electric transmission facilities. (2)  For purposes of this section the following definitions shall apply: (a)  "Electric transmission facilities" means the construction of high voltage transmission lines with an operating level capacity of two hundred thirty thousand (230,000) volts or more and associated substations and switchyards. (b)  "State agency" means every state department, division, commission or board. (3)  Any person intending to construct eligible electric transmission facilities in Idaho may file an application with the public utilities commission seeking priority designation. An order granting priority designation shall not constitute regulatory approval or bind any state agency. If the commission issues an order granting priority designation, state agencies subsequently involved in the permitting or siting processes for such electric transmission facilities shall be required to give the application priority or immediate attention as it relates to reviews, permits, reports, studies or comments. (4)  In reviewing an application for priority designation, the public utilities commission shall base its findings on whether the proposed construction of electric transmission facilities will: (a)  Benefit Idaho customers and the Idaho economy; (b)  Improve electric transmission capacity and reliability in Idaho and the region; and (c)  Promote the public interest. (5)  Applications for priority designation filed with the public utilities commission shall be governed by the commission’s rules of administrative procedure. The commission may promulgate administrative rules in compliance with chapter 52, title 67 , Idaho Code, or may issue procedural orders necessary to implement this section.

History:[61-516, added 2009, ch. 9, sec. 1, p. 11.]
Source: legislature.idaho.gov — public domain Official Source ↗
Root-LD Entity Data
◈ Machine-Readable Provenance Record Root-LD v1.0 · boisestandard.org
Federation ID
BS-IC61-SEC-C861BB
Entity Class
STATUTE / IDAHO-STATE-CODE-SECTION
Domain Signature
boisestandard.org
Jurisdiction
Idaho — United States
Citation
Idaho Code § 61-516
Status
✓ ACTIVE
Source
PRIMARY-SOURCE
Source Verified
✓ TRUE
Content Hash
aff9655caade5542...
Semantic Edges
Pending — corpus passes queued
The statutory text of Idaho Code § 61-516 is reproduced from the official Idaho Legislature website (legislature.idaho.gov), published by the Idaho Legislative Services Office. Idaho Code is public domain.
Navigate Corpus — Idaho Code Title 61
◈ Provenance
boisestandard.org United States Idaho Idaho Code Title 61 Idaho Code § 61-516